对竣工试验的干扰

时间:2022-09-23 百科知识 版权反馈
【摘要】:如果由于进行竣工试验的此项拖延,使承包商遭受延误和(或)招致增加费用,承包商应向雇主发出通知,有权根据第20.1款[承包商的索赔]的规定提出:If the Contractor is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employe

如果由雇主应负责的原因妨碍承包商进行竣工试验达14天以上,承包商应尽快地进行竣工试验.      

如果由于进行竣工试验的此项拖延,使承包商遭受延误和(或)招致增加费用,承包商应向雇主发出通知,有权根据第20.1款[承包商的索赔]的规定提出:

(a) 根据第8.4款[竣工时间的延长]的规定,如果竣工已或将受到延误,对任何此类延误给予延长期;

(b)  对任何此类费用,加合理的利润,应加入合同价格,给予支付.

雇主受到此通知后,应按照第3.5款[确定]的规定,对这些事项进行商定或确定.

If the Contractor is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Employer is responsible, the Contractor shall carry out the Tests on Completion as soon as practicable.

If the Contractor suffers delay and/or incurs Cost as a result of this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Employer and shall be entitled subject to Sub-Clause 20.1 [Contractors Claims] to:

(a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and

(b) payment of any such Cost plus reasonable profit, which shall be added to the Contract Price.

After receiving this notice, the Employer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.