延误的试验

时间:2022-09-23 百科知识 版权反馈
【摘要】:如果雇主不当地延误竣工试验,雇主可通知承包商,要求在接到通知后21天内进行竣工试验.承包商应在上述期限内的某日或某几日内进行竣工试验,并将该日期通知雇主.如果承包商未在规定的21天内进行竣工试验,雇主人员可自行进行这些试验.试验的风险和费用应由承包商承担.这些竣工试验应被视为是承包商在场时进行的,试验结果应认为准确,予以认可.If the Tests on Completion are being

如果雇主不当地延误竣工试验,雇主可通知承包商,要求在接到通知后21天内进行竣工试验.承包商应在上述期限内的某日或某几日内进行竣工试验,并将该日期通知雇主.

如果承包商未在规定的21天内进行竣工试验,雇主人员可自行进行这些试验.试验的风险和费用应由承包商承担.这些竣工试验应被视为是承包商在场时进行的,试验结果应认为准确,予以认可.

If the Tests on Completion are being unduly delayed by the Employer, Sub-Clause 7.4 [Testing] (fifth paragraph) and/or Sub-Clause 10.3 [Interference with Tests on Completion] shall be applicable.

If the Tests on Completion are being unduly delayed by the Contractor, the Employer may by notice require the Contractor to carry out the Tests within 21 days after receiving the notice. The Contractor shall carry out the Tests on such day or days within that period as the Contractor may fix and of which he shall give notice to the Employer.

If the Contractor fails to carry out the Tests on Completion within the period of 21 days, the Employers Personnel may proceed with the Tests at the risk and cost of the Contractor. These Tests on Completion shall then be deemed to have been carried out in the presence of the Contractor and the results of the Tests shall be accepted as accurate.