【摘要】:如果承包商没有在按照第14.7款[付款的时间安排]规定的时间收到付款,承包商应有权就未付款按月计算复利,收取延误期的融资费用.除非专用条件中另有规定,上述融资费用应以高出付款货币所在国中央银行的贴现率三个百分点的年利率进行计算,并应用同种货币支付.If the Contractor does not receive payment in accordance with Sub-Clause 14.

如果承包商没有在按照第14.7款[付款的时间安排]规定的时间收到付款,承包商应有权就未付款按月计算复利,收取延误期的融资费用.

除非专用条件中另有规定,上述融资费用应以高出付款货币所在国中央银行的贴现率三个百分点的年利率进行计算,并应用同种货币支付.

承包商应有权得到上述付款,无需正式通知,且不损害他的任何其他权利或对其补偿.

If the Contractor does not receive payment in accordance with Sub-Clause 14.7 [Timing of Payments], the Contractor shall be entitled to receive financing charges compounded monthly on the amount unpaid during the period of delay.

Unless otherwise stated in the Particular Conditions, these financing charges shall be calculated at the annual rate of three percentage points above the discount rate of the central bank in the country of the currency of payment, and shall be paid in such currency.

The Contractor shall be entitled to this payment without formal notice, and without prejudice to any other right or remedy.