【摘要】:如果承包商未能在合理的时间内修补任何缺陷和损害,雇主可确定一个日期,要求到或不迟于该日期修补好缺陷或损害,并应将该日期及时通知承包商。雇主还应有权,在不损害根据合同或其他规定所具有的任何其他权利的情况下,收回对工程或该部分工程的全部支出总额,加上融资费用和拆除工程、清理现场、以及将生产设备和材料退还给承包商所支付的费用。

如果承包商未能在合理的时间内修补任何缺陷和损害,雇主(或其代表)可确定一个日期,要求到或不迟于该日期修补好缺陷或损害,并应将该日期及时通知承包商。

如果承包商到该通知的日期仍未修补好缺陷或损害,且此项修补工作根据第11.2款[修补缺陷的费用]的规定应由承包商承担实施的费用,雇主可以(自行选择):

(a) 以合理的方式由他自己或他人进行此项工作,由承包商承担费用,但承包商对此项工作将不再负责任;承包商应按照第2.5款[雇主的索赔]的规定,向雇主支付由雇主修补缺陷或损害而发生的合理费用;

(b) 按照第3.5款[确定]的要求,商定或确定合同价格的合理的减少额;或

(c) 如果上述缺陷或损害使雇主实质上丧失了工程或工程的任何主要部分的整个利益时,终止整个合同,或其有关不能按原定意图使用的该主要部分。雇主还应有权,在不损害根据合同或其他规定所具有的任何其他权利的情况下,收回对工程或该部分工程(视情况而定)的全部支出总额,加上融资费用和拆除工程、清理现场、以及将生产设备和材料退还给承包商所支付的费用。

If the Contractor fails to remedy any defect or damage within a reasonable time, a date may be fixed by (or on behalf of) the Employer, on or by which the defect or damages is to be remedied. The Contractor shall be given reasonable notice of this date.

If the Contractor fail to remedy the defect or damage by this notified date and this remedial work was to be executed at the cost of the Contractor under Sub-Clause 11.2[Cost of Remedying Defects], the Employer may (at his option):

(a) carry out the work himself or by others, in a reasonable manner and at the Contractors cost, but the Contractor shall have no responsibility for this work; and the Contractor shall subject to Sub-Clause 2.5 [Employers Claims] pay to the Employer the costs reasonably incurred by the Employer in remedying the defect or damage;

(b) agree or determine a reasonable reduction in the Contract Price in accordance with Sub-Clause 3.5 [Determinations]; or

(c) if the defect or damage deprives the Employer of substantially the whole benefit of the Works or any major part of the Works, terminate the Contract as a whole, or in respect of such major part which cannot be put to the intended use. Without prejudice to any other rights, under the Contract or otherwise, the Employer shall then be entitled to recover all sums paid for the Works or for such part (as the case may be), plus financing costs and the cost of dismantling the same, clearing the Site and returning Plant and Materials to the Contractor.