为了使工程、承包商文件和每个分项工程在相应缺陷通知期限期满日期或其后尽快达到合同要求(合理的损耗除外),承包商应:

(a) 在雇主指示的合理时间内,完成接收证书注明日期时尚未完成的任何工作;

(b) 在工程或分项工程(视情况而定)的缺陷通知期限期满日期或其以前,按照雇主可能通知的要求,完成修补缺陷或损害所需要的所有工作.

如果出现缺陷,或发生损害,雇主应根据情况,通知承包商.

In order that the Works and Contractors Documents, and each Section ,shall be in the condition required by the Contract (fair wear and tear excepted) by the expiry date of the relevant Defects Notification Period or as soon as practicable thereafter, the Contractor shall:

(a) complete any work which is outstanding on the date stated in a Taking-Over Certificate, within such reasonable time as is instructed by the Employer, and

(b) execute all work required to remedy defects or damage, as may be notified by the Employer on or before the expiry date of the Defects Notification Period for the Works or Section (as the case may be)

If a defect appears or damage occurs, the Employer shall notify the Contractor accordingly.