【摘要】:除合同另有说明外:(a)承包商应被认为已取得了对工程可能产生影响和作用的有关风险、意外事件和其他情况的全部必要资料;(b)通过签署合同,承包商接受对预见到的为顺利完成工程的所有困难和费用的全部职责;(c)合同价格对任何未预见到的困难和费用不应考虑予以调整.Except as otherwise stated in the Cont

除合同另有说明外:

(a) 承包商应被认为已取得了对工程可能产生影响和作用的有关风险、意外事件和其他情况的全部必要资料;

(b) 通过签署合同,承包商接受对预见到的为顺利完成工程的所有困难和费用的全部职责;

(c) 合同价格对任何未预见到的困难和费用不应考虑予以调整.

Except as otherwise stated in the Contract:

(a) the Contractor shall be deemed to have obtained all necessary information as to risks, contingencies and other circumstances which may influence or affect the Works;

(b) by signing the Contract, the Contractor accepts total responsibility for having foreseen all difficulties and costs of successfully completing the Works; and

(c) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs.